Question: For Ford to designate a supplier as Q-1 (its highest designation), Ford requires that the supplier have a C p equal to 1.33. Currently your

For Ford to designate a supplier as Q-1 (its highest designation), Ford requires that the supplier have a Cp equal to 1.33. Currently your firm has Cp = 1. What must you do to increase your Cp to 1.33? Be as specific as possible.

Step by Step Solution

3.37 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Assuming the mean is currently on target and widening the specification limits ... View full answer