Question: Given the following information about a small project, a. Draw a network diagram. b. Identify the critical path, earliest start and finish and slack for

Given the following information about a small project,

Given the following information about a small project, 
a. Draw

a. Draw a network diagram.
b. Identify the critical path, earliest start and finish and slack for each task.
c. Which of these activities should the project manager track most closely?
d. What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?

Task Duration Iediate Estimates Predecessors None A 2 days B 5 days 1day D 2 days E 3 days B & D F 12 days E&C

Step by Step Solution

3.40 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b The critical path is A B E F Task Immediate Predecessors Earliest Start ES Earliest Completi... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

434-B-M-L-S-C-M (2530).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!