Question: Given the following information, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start

Given the following information, compute the early, late, and slack times for the project network. Which activities on the critical path have only the start or finish of the activity on the critical path?

14 15 12 Lights 12 26 27 27 н 27 28 23 25 Lag 1 Paint 11 14 Open Lot Pave Parkin Prepare Site Post Lines Signs 27 28 23

14 15 12 Lights 12 26 27 27 27 28 23 25 Lag 1 Paint 11 14 Open Lot Pave Parkin Prepare Site Post Lines Signs 27 28 23 25 Lag 10 26 27 11 3 14 25 26 20 14 19 22 23 17 1 Signage 1 Dig Trenches Lay Pipe Black Legend Fill 26 27 ES EF 10 14 19 17 22 20 23 SL Description SL LS Duration LF Lag 3 Lag 3 26

Step by Step Solution

3.33 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The critical path is ABDEFGHI 0 0 A Post Signs 1 1 Lag 10 E B Prepare 0 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1379-B-M-L-P-M(2677).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!