Question: Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path
Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the projectduration.
.png)
10 6 12 8 Start Finish 10 15 12 0 7
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
Critical path 2 6 9 11 38 month Start S1 108 8 19 2 0 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
300-B-F-F-M (3511).docx