Question: Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path

Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the projectduration.

Given the following network, with activity times in months, determine

10 6 12 8 Start Finish 10 15 12 0 7

Step by Step Solution

3.40 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Critical path 2 6 9 11 38 month Start S1 108 8 19 2 0 ... View full answer