Question: Given the following network, with activity times in weeks, determine the earliest and latest activity times and the slack for each activity. Indicate the critical
.png)
3 15 10 7 0 Start 6 7 12
Step by Step Solution
3.58 Rating (172 Votes )
There are 3 Steps involved in it
Critical path 1 3 8 34 weeks Start 1 ... View full answer