Question: Given the part mix, process routings, and processing times for the three parts in Problem 19.1. The FMS planned for this part family will operate
(a) The FMS operates 8 hours per day,
(b) 16 hours per day, and
(c) 24 hours per day.
(d) Which system configuration is preferred, and why?
Step by Step Solution
3.35 Rating (164 Votes )
There are 3 Steps involved in it
a Annual hours of operation 8 hrday250 daysyr 2000 hryr R p 2222 pchr 03704 pcmin From Problem 191 W... View full answer