Question: Given the part mix, process routings, and processing times for the four parts in Problem 19.3. The FMS proposed to machine these parts will operate

Given the part mix, process routings, and processing times for the four parts in Problem 19.3. The FMS proposed to machine these parts will operate 20 hours per day, 250 days per year. Assume system availability = 95%. Determine
(a) How many servers at each station will be required to achieve an annual production rate of 75,000 parts per year, and
(b) The utilization of each workstation.
(c) What is the maximum possible annual production rate of the system if the bottleneck station were to operate at 100% utilization?

Step by Step Solution

3.47 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a H 20 hrday250 daysyr 5000 hryr R p 15789 pchr 0263 pcmin From Problem 193 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

795-C-S-A-I (780).docx

120 KBs Word File

Students Have Also Explored These Related Artificial Intelligence Questions!