Question: Given the project information below, what is the probability of completing the National Holiday Toy project in 93 timeunits? Critical Act. ID Description Predecessor 0ptm.
Given the project information below, what is the probability of completing the National Holiday Toy project in 93 timeunits?
.png)
Critical Act. ID Description Predecessor 0ptm. (a Most likely (m) Pess. (b) Acttime t, Variance b - al/6 24 1 Design package None 2 Design product 12 19 28 39 10 16 Build package 4 Secure patent 2 5 Build product 21 17 30 29 3,4,5 Paint Test market 13 16
Step by Step Solution
3.39 Rating (168 Votes )
There are 3 Steps involved in it
Act ID Description Prede cessor Optm a Most Likely m Pess b Act time t e Var... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
177-B-M-L-P-M (1382).docx
120 KBs Word File