Question: Given the project information below, what is the probability of completing the National Holiday Toy project in 93 timeunits? Critical Act. ID Description Predecessor 0ptm.

Given the project information below, what is the probability of completing the National Holiday Toy project in 93 timeunits?

Given the project information below, what is the probability of

Critical Act. ID Description Predecessor 0ptm. (a Most likely (m) Pess. (b) Acttime t, Variance b - al/6 24 1 Design package None 2 Design product 12 19 28 39 10 16 Build package 4 Secure patent 2 5 Build product 21 17 30 29 3,4,5 Paint Test market 13 16

Step by Step Solution

3.39 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Act ID Description Prede cessor Optm a Most Likely m Pess b Act time t e Var... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

177-B-M-L-P-M (1382).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!