Question: Given the project shown in Figure of Chapter 5, assume that a facility used by activities c and d is scarce. To which activity would

Given the project shown in Figure of Chapter 5, assume that a facility used by activities c and d is scarce. To which activity would you assign the facility first, given the following rules?

(a) Minimum slack rule

(b) Most followers

(c) Most critical followers

(d) Shortest task first

(e) As late as possible

Step by Step Solution

3.52 Rating (179 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The following Table shows the activity slack critical followers duration and latest start time for ... View full answer