Question: Grant Construction Company was awarded a contract to construct an interchange at the junction of U.S. 94 and Highway 30 at a total contract price
Grant Construction Company was awarded a contract to construct an interchange at the junction of U.S. 94 and Highway 30 at a total contract price of $6,000,000. The estimated total costs to complete the project were $4,500,000.
Instructions
(a) Make the entry to record construction costs of $2,700,000, on construction in process to date.
(b) Make the entry to record progress billings of $1,500,000.
(c) Make the entry to recognize the profit that can be recognized to date, on a percentage-of-Completion basis.
Step by Step Solution
3.49 Rating (175 Votes )
There are 3 Steps involved in it
a Project Expenses AcDr 2700000 To Cash Material ... View full answer