Question: Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects is one of the firms bidding on the job.
Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects is one of the firms bidding on the job. Frey estimates that the job will require the following direct labor.
.png)
Frey applies overhead to jobs at 175% of direct labor cost. Frey would like to earn at least $ 80,000 profit on the architectural job. Based on past experience and market research, it estimates that the competition will bid between $ 285,000 and $ 350,000 for the job.
1. What is Frey’s estimated cost of the architectural job?
2. What bid would you suggest that Freysubmit?
Labor Estimated Hours Hourly Rate Architects Staff Clerical 150 300 500 $300 75 20
Step by Step Solution
3.55 Rating (166 Votes )
There are 3 Steps involved in it
1 Estimated cost of the architectural job Labor type Estimated hours Hourly rate Total cost Architec... View full answer
Get step-by-step solutions from verified subject matter experts