Question: Multiplex Corporation has requested bids from several architects to design its new corporate headquarters. Friesen Architects is one of the firms bidding on the job.
.png)
Friesen applies overhead to jobs at 160% of direct labor cost. Friesen would like to earn at least $80,000 profit on the architectural job. Based on past experience and market research, it estimates that the competition will bid between $325,000 and $400,000 for the job.
1. What is Friesens estimated cost of the architectural job?
2. What bid would you suggest that Friesensubmit?
Labor Estimated Hours Hourly Rate Architects Staff Clerical 200 400 700 $300 75 20
Step by Step Solution
3.56 Rating (170 Votes )
There are 3 Steps involved in it
1 Estimated cost of the architectural job Labor type Estimated hours Hourly rate Total cost Architec... View full answer