Question: How many kanbans would be needed in each case? a. Demand is increased to 200 avionic switches per hour. b. The lead time for components
a. Demand is increased to 200 avionic switches per hour.
b. The lead time for components is increased to 60 minutes.
c. The rack size is doubled.
d. The safety factor is increased to 10 percent.
Step by Step Solution
3.39 Rating (161 Votes )
There are 3 Steps involved in it
a d 200 switches per hour L4060067 hour C 25 switches You need 6 kanbans for the APP switch assembl... View full answer