Question: If the final consolidation settlement for the clay layer of Problem 9.1 is expected to be 1.5 m, how much settlement has occurred when the

If the final consolidation settlement for the clay layer of Problem 9.1 is expected to be 1.5 m, how much settlement has occurred when the time factor is

(a) 0.3

(b) 0.8?