In a work center, six machinists were uniquely qualified to operate any one of the five machines

Question:

In a work center, six machinists were uniquely qualified to operate any one of the five machines in the shop. The work center had considerable backlog, and all five machines were kept busy at all times. The one machinist not operating a machine was usually occupied doing clerical or routine maintenance work. Given the value schedule below for each machinist on each of the five machines, develop the optimal assignments. Assume only one machinist will be assigned to each machine.