Question: In Problem 4, assume that the workforce cost increases by $2,000 per worker and backordering is increased to $25 per unit per period. Which strategy
(a) Level production with overtime and subcontracting
(b) Pure level production strategy
(c) Pure chase strategy
(d) 2,500 units of regular production from March through September and as much regular, overtime, and subcontracting production in the other months as needed to meet annual demand.
Step by Step Solution
3.38 Rating (170 Votes )
There are 3 Steps involved in it
Workforce cost o Hiring cost per worker 2300 o Firing cost per worker 2400 a Use a level production ... View full answer