Question: In Problem 7, Set 8.1a, suppose that production strives to meet the quota for the two products, using overtime if necessary. Find a solution to

In Problem 7, Set 8.1a, suppose that production strives to meet the quota for the two products, using overtime if necessary. Find a solution to the problem, and specify the amount of overtime, if any, needed to meet the production quota.

Problem 7

Two products are manufactured on two sequential machines. The following table gives the machining times in minutes per unit for two products.

Machining time in min Machine Product ! Produçt 2 1 5 3 2 6 2 au


The daily production quotas for the two products are 80 and 60 units, respectively. Each machine runs 8 hours a day. Overtime, though not desirable, may be used if necessary to meet the production quota..

Machining time in min Machine Product ! Produt 2 1 5 3 2 6 2 au

Step by Step Solution

3.44 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Assign relatively large weight to the quota Constraint Min Z 100S 1 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

448-M-S-L-P (1518).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!