Question: Integrated, Inc., entered into a contract with the state of California to construct a building. It then subcontracted the electrical work to Alec Fergusson Electrical

Integrated, Inc., entered into a contract with the state of California to construct a building. It then subcontracted the electrical work to Alec Fergusson Electrical Contractors. The subcontract was a printed form with blanks filled in by typewriting. The printed payment clause required Integrated to pay Fergusson on the 15th day of the month following the submission of invoices by Fergusson. The typewritten part of the contract required Integrated to pay Fergusson “immediately following payment” (by the state) to the general contractor. When was payment required? [Integrated, Inc. v Alec Fergusson Electrical Contractors, 58 Cal Rptr 503 (Cal App)]

Step by Step Solution

3.29 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The court held that the typewritten provision on payme... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

131-L-B-L-C (855).docx

120 KBs Word File

Students Have Also Explored These Related Business Law Questions!