Question: Jack has asked you to calculate the following for Work Center 2. (a) Calculate the percentage of planned output needed to complete the planned inputs
Jack has asked you to calculate the following for Work Center 2.
(a) Calculate the percentage of planned output needed to complete the planned inputs (planned input + backlog/planned output) at Work Center 2.
(b) Calculate the percentage of planned input that actually happened (actual input + backlog/planned input + backlog) at Work Center 2.
(c) Calculate the percentage of available output that was actually accomplished (actual output/planned output) at Work Center 2.
(d) What insights can you offer Jack about Work Centers 2 and 3?
(a) Calculate the percentage of planned output needed to complete the planned inputs (planned input + backlog/planned output) at Work Center 2.
(b) Calculate the percentage of planned input that actually happened (actual input + backlog/planned input + backlog) at Work Center 2.
(c) Calculate the percentage of available output that was actually accomplished (actual output/planned output) at Work Center 2.
(d) What insights can you offer Jack about Work Centers 2 and 3?
Step by Step Solution
★★★★★
3.35 Rating (164 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
a 1 2 3 4 5 Total Planned input 40 50 50 60 60 ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
194-B-M-L-O-M (779).docx
120 KBs Word File