Question: Jack has asked you to calculate the following for Work Center 2. (a) Calculate the percentage of planned output needed to complete the planned inputs

Jack has asked you to calculate the following for Work Center 2.
(a) Calculate the percentage of planned output needed to complete the planned inputs (planned input + backlog/planned output) at Work Center 2.
(b) Calculate the percentage of planned input that actually happened (actual input + backlog/planned input + backlog) at Work Center 2.
(c) Calculate the percentage of available output that was actually accomplished (actual output/planned output) at Work Center 2.
(d) What insights can you offer Jack about Work Centers 2 and 3?

Step by Step Solution

3.35 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a 1 2 3 4 5 Total Planned input 40 50 50 60 60 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

194-B-M-L-O-M (779).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!