Question: Jane and Jim Smith are going to give a dinner party on Friday evening at 7:00 P.M. Their two children, Jerry and Judy, are going
Jane and Jim Smith are going to give a dinner party on Friday evening at 7:00 P.M. Their two children, Jerry and Judy, are going to help them get ready. The Smiths will all get home from work and school at 4:00 P.M. Jane and Jim have developed a project network to help them schedule their dinner preparations. Following is a list of the activities, the precedence relationships, and the activity times involved in the project:
.png)
Develop a project network and determine the earliest and latest start and finish times, activity slack, and critical path. Compute the probability that they will be ready by 7:00P.M.
Time Estimates (min.) Activity Predecessor a Activity 1 Cut and prepare vegetables Jane shower and dress Uncork wine/water carafes n Prepare and set out dishes Heat vegetable dish 7 t appetizers
Step by Step Solution
3.40 Rating (162 Votes )
There are 3 Steps involved in it
Start b m Finish Activity Project a b d e f 8 h m n 0 P 9 Time 160833 24833 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
300-B-F-F-M (3524).docx
120 KBs Word File