Question: Jobs A, B, C, D, and E must go through Processes I and II in that sequence (Process I first, then Process II). Use Johnsons
Jobs A, B, C, D, and E must go through Processes I and II in that sequence (Process I first, then Process II). Use Johnson’s rule to determine the optimal sequence in which to schedule the jobs to minimize the total requiredtime.
.png)
REQUIRED PROCESSING TIME ON I REQUIRED PROCESSING TIME ON II JoB A. 4 16 14 12
Step by Step Solution
3.38 Rating (173 Votes )
There are 3 Steps involved in it
Job Process I Time Process II Time Order ... View full answer