Just Nuts, a macadamia nut cannery, is analyzing its throughput for September. The following statistics are obtained for the month:
Cans packed and sold ..........700,000
Total cans packed ............742,040
Value-added processing time ...... 650 hours
Total processing time ......... 2,450 hours
a. Calculate the manufacturing cycle efficiency.
b. Calculate the process productivity.
c. Calculate the process quality yield.
d. Calculate the throughput using only good units and total time.
e. Verify your answer to (d) by using your answers to (a), (b), and (c).
Step by Step Solution
3.34 Rating (157 Votes )
There are 3 Steps involved in it
a MCE Valueadded time Total time 650 2450 2653 rounded b Process productiv... View full answer