Question: La Maya Corp. wants to compute its throughput for August 2010. The following production data are available: Good units produced and sold.......2,923,200 Total units produced........................3,360,000
La Maya Corp. wants to compute its throughput for August 2010.
The following production data are available:
Good units produced and sold.......2,923,200
Total units produced........................3,360,000
Total processing time..........................144,000 hours
Value-added time..................................50,400 hours
a. Determine the manufacturing cycle efficiency.
b. Determine the process productivity.
c. Determine the process quality yield.
d. Determine the throughput.
e. What can company management do to raise hourly throughput?
Step by Step Solution
3.38 Rating (170 Votes )
There are 3 Steps involved in it
a MCE Valueadded time Total time 50400 144000 35 b Process productivity Total un... View full answer