Lee Corp. is looking to introduce a new product with an 80% cumulative learning curve for production

Question:

Lee Corp. is looking to introduce a new product with an 80% cumulative learning curve for production batches of 500 units. The variable production and selling costs, all subject to learning, are $20 per unit for the first 1,000-unit batch. There are $15,000 in fixed costs not subject to learning
What is the average cost per unit at a production level of 2,000 units?  a. $18.20 b. $23.50 c. $26.40 d. $32.60