Match each item on the left with the most appropriate item on the right.
1. “Ad hoc” processes.......... a. Test (SDLC)
2. Business rules............ b. Risk of SDLC
3. Consistent project standards. c. Repeatable (CMM)
4. Cost overrun....... d. Optimized (CMM)
5. Discrete project standards... e. Managed (CMM)
6. Feasibility study....... f. Initiation/planning (SDLC)
7. Improvement part of organizational culture.. g. Design (SDLC)
8. Modular programming code......... h. Defined (CMM)
9. Simulations............. i. Chaotic (CMM)
10. Statistical project control...... j. Build (SDLC)
Step by Step Solution
3.45 Rating (174 Votes )
There are 3 Steps involved in it
1 i Chaotic CMM 2 g Design SDLC 3 h ... View full answer