Question: Mining over the years produces a tabular excavation that extends about 2,000 ft (610 m) down dip from the surface. Dip of the ore zone
Mining over the years produces a tabular excavation that extends about 2,000 ft (610 m) down dip from the surface. Dip of the ore zone is 65◦, width is 40 ft (12.2 m). Strike length is over 6,000 ft (1,839 m). Estimate the peak stresses and indicate their location on a sketch of the mine.
Step by Step Solution
3.39 Rating (155 Votes )
There are 3 Steps involved in it
Given Tabular excavation 65 dip 40 ft thick 6000 ft on strike 2000 ft down dip Find Pe... View full answer