Moravia Company processes and packages cream cheese. The following data have been compiled for the month of April. Conversion activity occurs uniformly throughout the production process.

Work ii process, April 1—10,000 units:

Direct material: 100% complete, cost of ....................................................................................... $ 22.000

Conversion: 20% complete, cost of ..................................................................................................... 4500

Balance in work in process, April 1 ............................................................................................... $ 26.500

Units started during April ................................................................................................................ 100,000

Units completed during April and transferred out to finished goods inventory........................ 80,000

Work in process April 30:

Direct material: 100% complete

Conversion: 33MG complete

Costs incurred during April:

Direct material ................................................................................................................................ $198,000

Conversion costs:

Direct labor ........................................................................................................................................ $ 52800

Applied manufacturing overhead ................................................................................................... 105,600

Total conversion casts ..................................................................................................................... $158,400


Required: Prepare schedules to accomplish each of the following process-costing steps for the month of April. Use the weighted-average method of process costing.

1. Analysis of physical flow of units.

2. Calculation of equivalent units.

3. Computation of unit costs.

4. Analysis of total costs.

5. Build a spreadsheet: Construct an Excel spreadsheet to solve all of the preceding requirements. Show how the solution will change if the following data change: the April 1 work-in-process costs were $66,000 for direct material and $18,000 for conversion.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Accounting

ISBN: 9780073022857

7th Edition

Authors: Ronald W Hilton

Question Posted: