Question: Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows: The critical path calculation shows
Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows:
-1.png)
-2.png)
The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant:
a. Formulate a linear programming model that can be used to make the crashing decisions for this project.
b. Solve the linear programming model and make the minimum cost crashing decisions. What is the added cost of meeting the 16-week completion time?
c. Develop a complete activity schedule based on the crashed activitytimes.
Activty Time Activity Time A C Start H Finish Time (weeks) Cost (S) Nor Crash Norma Crash 1700 4000 1000 Activity ormal 900 2000 500 1800 1500 3000 8000 1000 1850 9800
Step by Step Solution
3.34 Rating (169 Votes )
There are 3 Steps involved in it
a Activity Maximum Crash Crash CostWeek A 2 400 B 3 667 C 1 500 D 2 300 E 1 350 F 2 450 ... View full answer