Question: Consider the following project network and activity times (in days): The crashing data for this project are as follows: a. Find the critical path and
Consider the following project network and activity times (in days):
-1.png)
-2.png)
The crashing data for this project are as follows:
-3.png)
a. Find the critical path and the expected project completion time.
b. What is the total project cost using the normaltimes?
Start Finish Activity | A B C D E F G Time 132 5 5 62 2 Cost ($) Time (days Norma Crash Nora Crash 1400 1900 2800 2300 2800 Activity 800 1200 2000 1500 1800 600 500 Cost ($) Time (days) NormCrash Nor Crash 1400 1900 2800 2300 2800 1000 1000 Activity )() 1200 2000 1500 1800 600 500
Step by Step Solution
3.42 Rating (158 Votes )
There are 3 Steps involved in it
a Activity Earliest Start Latest Start Earliest Finish Latest ... View full answer