Question: Office Automation, Inc., developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company.

Office Automation, Inc., developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:



Office Automation, Inc., developed a proposal for introducing a


a. Develop a project network.
b. Develop an activity schedule.
c. What are the critical activities, and what is the expected project completion time?
d. Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
e. Develop an activity schedule for the crashed project.
f. What added project cost is required to meet the six-month completiontime?

Fime (weeks) Cost (SIO00s) Immediate Predecessor Activit Description Normal 10 10 10 Crash Normal 70 150 160 Plan needs Order equipment Install equipment Set up training lab Conduct training course Test system 120 100 6 75 C, E

Step by Step Solution

3.43 Rating (182 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b Activity Earliest Start Latest Start Earliest Finish Late... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

148-M-S-Q-M (54).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!