Question: PROJECT & OPERATIONS MANAGEMENT question Q3(a)-Develop a project network with detail of duration of the project, early start, early finish, latest start and latest finish

PROJECT & OPERATIONS MANAGEMENT question

PROJECT & OPERATIONS MANAGEMENT question

Q3(a)-Develop a project network with detail of duration of the project, early start, early finish, latest start and latest finish for each activity.

Q3(b)-What are the critical activities, and what is the expected project completion time?

Q3(c)-Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and show all your step.

Q3(d)-Develop project network for the crashed project with detail of duration of the project, early start, early finish, latest start and latest finish for each activity.

Q3(e)-What added project cost is required to meet the six-month completion time

Q3. Office Automation, Inc., developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities Activity Predecessor A B D E F Table Q3 Time (weeks) Normal Crash 10 8 8 6 10 7 7 6 10 8 3 3 A B D C, E Cost ($1000s) Normal Crash 30 70 120 150 100 160 40 50 50 75 60

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!