Question: Office Pro, Inc., does software development. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that
Instructions
1. If the team generated 6,000 lines of code according to the original plan, what would have been the labor time variance?
2. What was the actual labor time variance as a result of generating 7,000 lines of code?
3. What was the labor rate variance as a result of the bonus?
4. The manager is trying to determine if a better decision would have been to hire a temporary programmer to meet the higher programming demand in the first week of May, rather than paying out the bonus. If another employee was hired from the employment firm, what would have been the labor time variance in the first week?
5. Which decision is better, paying the bonus or hiring another programmer?
6. Are there any performance-related issues that the labor time and rate variances fail to consider? Explain.
Step by Step Solution
3.47 Rating (167 Votes )
There are 3 Steps involved in it
1 2 3 4 5 Hiring an extra employee is more costly than the bonus by 160 The cost variance for payin... View full answer