Omega Technology is starting production of a new supercomputer for use in large research universities. They have

Question:

Omega Technology is starting production of a new supercomputer for use in large research universities. They have just completed the first unit, which took 120 man-hours to produce. Based on their experience, they estimate their learning percentage to be 80%. How many man-hours should they expect the second unit to require to manufacture?