Question: On average, each unit produced by the Kantor Company takes 0.90 worker hours and 0.02 hours of machine time. Furthermore, each worker and machine is
On average, each unit produced by the Kantor Company takes 0.90 worker hours and 0.02 hours of machine time. Furthermore, each worker and machine is available
160 hours a month. Use these planning values and the following sales forecast to estimate (1) The number of worker hours and machine hours needed each month and
(2) The number of workers and machines needed each month.
Round your estimates of the number of workers and machines needed to the nearest whole number.
MONTH SALES FORECAST
October......... 44,000
November......... 52,000
December......... 68,000
January......... 69,000
February......... 58,000
March......... 46,000
Step by Step Solution
3.41 Rating (157 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style16 msonumberformat 000 000 00220022 msostylenameComma msostyleid3 style... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
436-B-M-L-S-C-M (2749).xlsx
300 KBs Excel File