Question: On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The
On March 1, 2017, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below.
.png)
Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore incomes taxes.)
2017 S2,880,000 3,520,000 2018 2019 $2,230,000 $2,190,000 Contract costs incurred during the year Estimated costs to complete the contract at 12/31 Billings to Fabrik during the year 2,190,000 3,500,000 3,200,000 1,700,000
Step by Step Solution
3.53 Rating (163 Votes )
There are 3 Steps involved in it
a Computation of Recognizable ProfitLoss PercentageofCompletion Method 2017 Costs to date 12311... View full answer