Question: On March 1, 2019, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The
On March 1, 2019, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2021. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2019, 2020, and 2021 are given below.
.png)
Instructions
a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2019, 2020, and 2021. (Ignore income taxes.)
b. Using the cost-recovery method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2019, 2020, and 2021. (Ignore incomes taxes.)
2021 2019 2020 Contract costs incurred during the year Estimated costs to complete the contract at 12/31 3,520,000 Billings to Fabrik during the year $2,880,000 $2,230,000 $2,190,000 -0- 2,190,000 3,200,000 3,500,000 1,700,000
Step by Step Solution
3.48 Rating (171 Votes )
There are 3 Steps involved in it
a Computation of Recognizable ProfitLoss PercentageofCompletion Method 2019 Costs to date 123119 28... View full answer
Get step-by-step solutions from verified subject matter experts