Question: One technique for operating a steam turbine in part-load power output is to throttle the steam to a lower pressure before it enters the turbine.
One technique for operating a steam turbine in part-load power output is to throttle the steam to a lower pressure before it enters the turbine. The steam line conditions are 200 lbf/in 2, 600 F, and the turbine exhaust pressure is fixed at 1 lbf/in 2. Assuming the expansion inside the turbine to be reversible and adiabatic, determine
a. The full-load specific work output of the turbine
b. The pressure the steam must be throttled to for 80% of full-load output
c. Show both processes in a T–s diagram.
Step by Step Solution
3.47 Rating (163 Votes )
There are 3 Steps involved in it
T P1 2a 3a 3b P2b 2b iconst S a CV Turbine fullload reversible 3... View full answer