Question: ONeil, Inc. began work on a $7,000,000 contract in 2010 to construct an office building. ONeil uses the percentage-of-completion method. At December 31, 2010, the
O’Neil, Inc. began work on a $7,000,000 contract in 2010 to construct an office building. O’Neil uses the percentage-of-completion method. At December 31, 2010, the balances in certain accounts were: construction in process $2,450,000; accounts receivable $240,000; and billings on construction in process $1,400,000. Indicate how these accounts would be reported in O’Neil’s December 31, 2010 balance sheet.
Step by Step Solution
3.53 Rating (170 Votes )
There are 3 Steps involved in it
Current Assets Accounts Receivable 240... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
11-B-A-R-R (35).docx