Question: ONeil, Inc. began work on a $7,000,000 contract in 2014 to construct an office building. ONeil uses the percentage-of-completion method. At December 31, 2014, the
O’Neil, Inc. began work on a $7,000,000 contract in 2014 to construct an office building. O’Neil uses the percentage-of-completion method. At December 31, 2014, the balances in certain accounts were Construction in Process $2,450,000; Accounts Receivable $240,000; and Billings on Construction in Process $1,400,000. Indicate how these accounts would be reported in O’Neil’s December 31, 2014, balance sheet.
Step by Step Solution
3.39 Rating (171 Votes )
There are 3 Steps involved in it
In ONeils December 31 2014 balance sheet the Construction in Process account would be reported as a ... View full answer