Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives.
Question:
_________________________Activity Cost Activity Base
Procurement...............................$370,000.............................Number of purchase orders
Scheduling...................................250,000..........................Number of production orders
Materials handling.......................500,000............................................Number of moves
Product development..................730,000......................Number of engineering changes
Production................................1,500,000.................................................Machine hours
1. Determine the activity rate for procurement per purchase order.
a. $43.53
b. $18.50
c. $15.42
d. $37.00
2. Determine the activity rate per production order for scheduling.
a. $200.00
b. $20.00
c. $29.41
d. $10.42
3. Determine the activity rate for materials handling per move.
a. $58.82
b. $50.00
c. $20.83
d. $80.65
4. Determine the activity rate for product development per change.
a. $73,000
b. $8,588
c. $30,417
d. $16,222
5. Determine the activity rate for production per machine hour.
a. $62.50
b. $150.00
c. $75.00
d. $176.47
6. Determine the activity-based cost for each disk drive unit.
a. $92.25
b. $130.69
c. $394.12
d. $279.57
7. Determine the activity-based cost for each wire drive unit.
a. $204.13
b. $173.51
c. $744.06
d. $394.12
8. Determine the activity-based cost for each tape drive unit.
a. $97.73
b. $232.69
c. $394.12
d. $103.84
A Corporation is a legal form of business that is separate from its owner. In other words, a corporation is a business or organization formed by a group of people, and its right and liabilities separate from those of the individuals involved. It may...
Step by Step Answer:
Financial and Managerial Accounting the basis for business decisions
ISBN: 978-0078111044
16th edition
Authors: Jan Williams, Susan Haka, Mark Bettner, Joseph Carcello