Question: Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching- board assembly lines. Determine the size of the kanban for subassemblies and
Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching- board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.
Setup cost= + 30
Annual holding cost = + 120 per subassembly
Daily production = 20 subassemblies
Annual usage = 2,500 (50 weeks * 5 days each * daily usage of 10 subassemblies)
Lead time = 16 days
Safety stock = 4 days> production of subassemblies.
Step by Step Solution
3.40 Rating (169 Votes )
There are 3 Steps involved in it
Pauline Found Manufacturing First we determine the kanban size To do this we determine the producti... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
286-B-M-L-O-M (2593).docx
120 KBs Word File