Question: Phan Company provided the following information: Standard variable overhead rate (SVOR) per direct labour hour ...................$3.70 Actual variable overhead rate (AVOR) per direct labour hour
Phan Company provided the following information:
Standard variable overhead rate (SVOR) per direct labour hour ...................$3.70
Actual variable overhead rate (AVOR) per direct labour hour .....................$3.68
Actual direct labour hours worked (AH) .............................................$6,200
Actual production in units ...............................................................14,000
Standard hours allowed for actual units produced (SH) .............................56,000
Required:
1. Using the columnar approach, calculate the variable overhead spending and efficiency variances.
2. Using the formula approach, calculate the variable overhead spending variance.
3. Using the formula approach, calculate the variable overhead efficiency variance.
4. Calculate the total variable overhead variance
Step by Step Solution
3.51 Rating (168 Votes )
There are 3 Steps involved in it
1 Columnar approach 1 AH AVOR 56200 368 2 AH SVOR 56200 370 3 SH SVOR 56000 370 206816 2079... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1348-B-M-A-P-C(3741).docx