PM Computer Services (described in Example) has received an order for 120 custom configured personal computers for

Question:

PM Computer Services (described in Example) has received an order for 120 custom configured personal computers for a local business. Paulette and Maureen have so many orders that they can no longer perform the work themselves, and they must hire extra labor to assemble the units for this new order. They have hired eight students from the university to work part-time, 20 hours per week, to assemble the computers. Paulette and Maureen assembled a prototype unit and it required 26 hours of direct labor; from experience they know their computer assembly operation has an 84% learning curve. Approximately when will PM Computer Services be able to deliver the completed order?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: