Question: Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 =

Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line.
a. Find the production capacity of the line for the following assignment: Worker 1 → Task 1, Worker 2→ Task 2, Worker 3→Tasks 3,4, Worker 4 → Tasks 5,6.
b. Find optimal assignment (to maximize the production capacity) if the task sequence should not be broken (task j should be done before task j +1).
c. Find optimal assignment (to maximize the production capacity) if the task sequence can be broken (no precedence relationship between tasks).

Step by Step Solution

3.36 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The bottleneck is worker 3 having processing time of 3540 75 seconds So the production capacit... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-A-S-S(149).docx

120 KBs Word File

Students Have Also Explored These Related Cost Accounting Questions!