Question: Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 =
Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line. a. Find the production capacity of the line for the following assignment: Worker 1 → Task 1, Worker 2→ Task 2, Worker 3→Tasks 3,4, Worker 4→ Tasks 5,6. b. Find optimal assignment (to maximize the production capacity) if the task sequence should not be broken (task j should be done before task j +1). c. Find optimal assignment (to maximize the production capacity) if the task sequence can be broken (no precedence relationship between tasks). 1 d. Assume that the daily demand for this item is 400 and that each worker costs 15 TL/hr. Find the direct labor cost per item if the task sequence should not be broken.
Step by Step Solution
3.41 Rating (164 Votes )
There are 3 Steps involved in it
a Cycle time of Worker1 30 sec Cycle time of Worker2 25 sec Cycle time of Worker3 75 sec Cycle time ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1019-B-C-A-S-S(674).docx
120 KBs Word File