Question: Reconstruct the example problem at the end of this chapter as an AOA network. Assume that the most likely times (m) are the normal activity

Reconstruct the example problem at the end of this chapter as an AOA network. Assume that the most likely times (m) are the normal activity times and that the optimistic times (a) are the activity crash times. Further assume that the activities have the following normal and crash costs:

Reconstruct the example problem at the end of this chapter

a. Formulate the general linear programming model for this project network, using most likely activity times (m).
b. Formulate the linear programming crashing model that would crash this network by the maximum amount.
c. Solve this model by using thecomputer.

Costs (normal cost, crash cost) Activity (2, 3) (2, 4) (3, 4) (3, 5) (4, 5) ($100, $400) ($250, $400) ($400, $800) ($200, $400) ($150, $300) (S100, $100) ($300, $500)

Step by Step Solution

3.48 Rating (171 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Minimize Z x 5 subject to x 2 x 1 8 x 3 x 1 10 x 3 x 2 5 x 4 x 2 3 x 4 x 3 6 x 5 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

300-B-F-F-M (3539).docx

120 KBs Word File

Students Have Also Explored These Related Finance Questions!