Question: Reconstruct the example problem at the end of this chapter as an AOA network. Assume that the most likely times (m) are the normal activity
.png)
a. Formulate the general linear programming model for this project network, using most likely activity times (m).
b. Formulate the linear programming crashing model that would crash this network by the maximum amount.
c. Solve this model by using thecomputer.
Costs (normal cost, crash cost) Activity (2, 3) (2, 4) (3, 4) (3, 5) (4, 5) ($100, $400) ($250, $400) ($400, $800) ($200, $400) ($150, $300) (S100, $100) ($300, $500)
Step by Step Solution
3.48 Rating (171 Votes )
There are 3 Steps involved in it
a Minimize Z x 5 subject to x 2 x 1 8 x 3 x 1 10 x 3 x 2 5 x 4 x 2 3 x 4 x 3 6 x 5 ... View full answer