Question: For the Solved Problem at the end of this chapter, assume that the most likely times (m) are the normal activity times and the optimistic
For the Solved Problem at the end of this chapter, assume that the most likely times (m) are the normal activity times and the optimistic times (a) are the activity crash times. Further assume that the activities have the following normal and crash costs:
Activity Costs (Normal Cost, Crash Cost)
1 ........($100, 400)
2 .....($250, 400)
3 ......($400, 800)
4 .....($200, 400)
5 .....($150, 300)
6 ......($100, 100)
7 .......($300, 500)
Crash the network the maximum amount possible and indicate the total crash cost.
Step by Step Solution
3.35 Rating (164 Votes )
There are 3 Steps involved in it
Project completion time 23 Normal cost 1500 Minimum project completion time 15 Cr... View full answer