Question: Refer to the Groovy Bottles Data Set in E10-53B. In Exercise Groovy Bottles is a manufacturer of ceramic bottles. The company has the following standards:
Refer to the Groovy Bottles Data Set in E10-53B.
In Exercise Groovy Bottles is a manufacturer of ceramic bottles. The company has the following standards:
Direct materials (clay)....................... 1.3 kg per bottle, at a cost of $0.40 per kg
Direct labour...................................... 1/5 hour per bottle, at a cost of $14.80 per hour
Static budget variable overhead............................ $70,500
Static budget fixed overhead ................................. $30,500
Static budget direct labour hours................................. 10,000 hours
Static budget number of bottles.................................... 52,000
Groovy Bottles allocates manufacturing overhead to production based on standard direct labour hours. Last month the company reported the following actual results for the production of 69,000 bottles:
Direct materials........................................ 1.5 kg per bottle, at a cost of $0.70 per kg
Direct labour............................................. 1/4 hour per bottle, at a cost of $12.90 per hour
Actual variable overhead.......................... $104,600
Actual fixed overhead .............................. $ 28,700
Requirements
1. Compute the direct labour price variance and the direct labour efficiency variance.
2. What is the total flexible budget variance for direct labour?
3. Who is generally responsible for each variance?
4. Interpret the variances.
Step by Step Solution
3.46 Rating (159 Votes )
There are 3 Steps involved in it
Req 1 Direct labour price variance Actual price Standard price Actual quantity per input unit per in... View full answer