Question: Refer to the previous question. Suppose a partner in Koene Technology does not believe the time estimates for each activity can be specified with certainty.

Refer to the previous question. Suppose a partner in Koene Technology does not believe the time estimates for each activity can be specified with certainty. Instead, he prefers to specify a minimum, most likely, and maximum number of days for each activity. These estimates are given in the following table.



Refer to the previous question. Suppose a partner in Koene


a. Use PERT to identify the expected time and variance for each activity.
b. What is the critical path? What is the expected time and variance for this path?
c. Assume that the distribution of the completion time for the critical path is normally distributed. What is the probability that it will take at least 40 days to complete theproject?

841079080019 221121 1 ast ly el k-111-1 09384435546897 56058224334565 IN A B C D E F G H I JK L M N

Step by Step Solution

3.34 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Activity Description Predecessor min most likely max Time EST EFT LST LFT Slack Variance A ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

167-B-M-L-M-D-A (334).xlsx

300 KBs Excel File

Students Have Also Explored These Related Management Leadership Questions!