Resolve Problem 8b using MSP. Omit the calculations for CPI, SPI, and CSI. Problem 8b Repeat the

Question:

Resolve Problem 8b using MSP. Omit the calculations for CPI, SPI, and CSI.

Problem 8b

Repeat the calculations in a, but now using the “% Complete” column. Assume that the PV values are based on time proportionality but the “% Complete” values for EV are from the workers actually doing the tasks.


Actual Cost, S Budget, $ % Complete 300 400 100 200 180 100 250 300 100 600 400 20 400 200 20


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470226216

7th Edition

Authors: Jack R. Meredith, Samuel J. Mantel,

Question Posted: