Question: Resolve Problem 8b using MSP. Omit the calculations for CPI, SPI, and CSI. Problem 8b Repeat the calculations in a, but now using the %
Resolve Problem 8b using MSP. Omit the calculations for CPI, SPI, and CSI.
Problem 8b
Repeat the calculations in a, but now using the “% Complete” column. Assume that the PV values are based on time proportionality but the “% Complete” values for EV are from the workers actually doing the tasks.

Actual Cost, S Budget, $ % Complete 300 400 100 200 180 100 250 300 100 600 400 20 400 200 20